Restoring Reflection
Restoring Reflection
Henry® Prodeq™ System Preserves Water Features at The Connor Group
Project Details
Project Owners: The Connor Group
Location: Miamisburg, Ohio
Square Footage: 5,000 sq ft
Architect: Moody Nolane
General Contractor: ZSR Contracting and Restoration, Inc
Waterproofing Contractor: ZSR Restoration
Henry Representatives: Edward Glace, Steve Tauchen, David Ritacco
Products Used
Henry® Prodeq™ FX600
Henry® Pumadeq™ Primer 20
Henry® GC Primer
CCW-201
At The Connor Group headquarters in Miamisburg, Ohio, reflecting pools accent the exterior of the building as a signature design feature. Over time, leaks compromised their performance. The project called for a durable repair that would restore water retention and ensure the pools could continue enhancing the architecture of the site. The Connor Group selected ZSR Restoration, a contractor known for its repair and restoration expertise, to address the failing 5,000 square feet of reflecting pool surface. The contractor was tasked with diagnosing the issues and recommending a long-term solution. After evaluating the conditions, the ZSR turned to Henry® Advanced Waterproofing Solutions for their durability, cost-effectiveness and proven performance. With technical support from Henry Technical Sales Representative Edward Glace and Steve Tauchen, the Prodeq™ System was selected as the best fit for the project.
Addressing Persistent Leaks
Years of water loss had exposed the failure of earlier coatings. Moisture was seeping through both the concrete surfaces and stainless steel verticals, leaving the reflecting pools unable to perform as intended. Restoringwatertightness was the first priority before any visual or functional improvements could be made. ZSR Restoration crews began by removing the failed coatings with grinders, scrapers, and hand tools to prepare the substrate for new materials. The tedious preparation steps were critical to ensure adhesion and long-term performance of the Prodeq System. Daily rain created complications, delaying progress by nearly three weeks. To keep the work on track, ZSR Restoration contractors coordinated closely with Glace and Tauchen, who provided ongoing technical and field support.
Detailing Complex Features
The pools were designed with drains, bubblers, lighting fixtures, and granite bullnose edges that required careful protection. Stainless steel vertical walls had been exposed to years of moisture, making them especially vulnerable. These elements demanded precise detailing to ensure long-term integrity once restored. “Moisture was a major concern, especially at the stainless steel wall that had been leaking for years,” said Glace. “Every detail had to be addressed to stop water loss once and for all.”
Installing a Lasting System
In addition to Prodeq, the restoration relied on other time-tested Henry products. Henry® GC Primer was applied in two coats to stabilize the concrete surfaces and control residual moisture. For the stainless steel elements, Pumadeq™ Primer 20 was used to achieve strong adhesion on non-porous substrates. CCW-201, a trowel-grade sealant, was placed around drains, fixtures, and transitions where water pressure posed the greatest risk.The system was completed with Prodeq™ FX600, a fluid-applied, instant-setting membrane selected for its seamless coverage and rapid cure. The product’s instant setting performance allowed crews to inspect and correct work the same day, keeping the job on-track and on-budget.
"The instant-setting membrane gave us the ability to check and correct our work the same day,” said a ZSR Restoration project manager. “That was a big advantage in keeping the
job moving while still paying attention to detail.”